← Infrastructure/Huawei Cloud East China (Wuhu) Data Center

Huawei Cloud East China (Wuhu) Data Center

D

Wuhu, Anhui, China · CN · Huawei

OperationalAI-Capable HyperscalePartially Verified

Environment

Water Stress
mediumB

WRI Aqueduct 4.0 (2023), province baseline water stress: Medium - High (20-40%), 2023

Aquifer Stress
Not DisclosedND
Grid Carbon Intensity
655 gCO₂/kWhA

China Ministry of Ecology and Environment, 2023 provincial average grid CO2 emission factor (Announcement 2025 No. 47), 2023

Grid RegionEast China Grid (Anhui)
Drought Risk
Not DisclosedND

Facility

CompanyHuawei
CategoryAI-Capable Hyperscale
StatusOperational
Year Opened2024
Capacity
Not DisclosedND

Not disclosed. Planned across three campuses on about 400 hectares, for up to three million servers.

Location
31.1800, 118.2100 · CN
Campus AreaCoordinates are the centre of Wuhu (OpenStreetMap), not the exact campus location.
RegionWuhu, Anhui, China
Research statusPartially Verified

Evidence (1 source)

Journalism2024-06-14TMTPost (钛媒体)

Confirms operator Huawei Cloud, Wuhu location and three campuses, opening in June 2024 as the first cluster project to open service, planned server count, PUE 1.1; no MW figure

华为云华东(芜湖)数据中心... 总占地6000亩... 规划了300万台服务器 (The Huawei Cloud East China (Wuhu) data centre covers 6,000 mu across three campuses (Jiangbei, Sanshan, Vocational Education Park), with 3 million servers planned. Liquid-cooled PUE as low as 1.1.)

Researcher Notes

Opened in June 2024 as the first project in the Wuhu national data center cluster. Huawei reports a liquid-cooled PUE as low as 1.1.