Google Project Mica Data Center Campus (Kansas City Northland, Missouri)
DKansas City, Missouri, US · US · Google (Alphabet Inc.)
Environment
Facility
Google confirmed in Feb 2026 a second Kansas City campus, 'Project Mica', on ~500 acres with five data centers (~1.56M sq ft). Port KC authorised up to $10B in bonds and 25-year tax breaks; first phase anticipated to take 18 months from site prep to first building. Google's first Missouri campus (Hunt Midwest, ~$1B) is separate.
Evidence (1 source)
Project status as of 2026-10-26
The site is known as Project Mica, according to Google.
Community
Evergy supplies power; Google agreed to cover full energy costs for both KC campuses (per Port KC/coverage). Evergy could not confirm whether residential rates could rise.
Community flags document events recorded in public sources. They do not imply causal attribution or ongoing harm.
Researcher Notes
Added 2026-10-26 from online research; coordinates are town-level unless noted.